Houston & Van Weiss Extensions (Mall Road Project)
& Intersection at Kimberly Drive and Ramsey Street.
The City has awarded a bid of $871,957.55 to Mike Nelson
Concrete Paving Company for reconstruction of Huston Street and Van
Weiss Boulevard on the north and east side of of Westland Mall and
the intersection at Kimberly Drive and Ramsey Street. The work
has started and the contractor has 70 working days to complete the
project.
The street will be a concrete street with curb and gutter. The
project includes removing existing pavement; earthwork; scarifying and
compacting the subgrade; constructing a granular subbase; removing and
constructing storm sewer pipe and intakes; constructing the pavement;
constructing longitudinal subdrains; finish grading; and seeding.
General Obligation Bonds will be issued to pay for the project.
The bonds will be repaid using Tax Increment Financing Proceeds.
Map of proposed street
improvements
Drainage Improvements at Broadway Avenue and
Agency Rd and Reconstruction of Intersection
French-Reneker-Associates has been contracted to offer
engineering services in connection with the storm sewer from
Division Street to the intersection of Agency Road and Broadway and
the reconstruction of the Intersection.
The construction bid was awarded to Langman Construction in the
amount of $999,361.01. The construction is to be 120 working
days starting no later than August 15th.
General Obligation Bonds will be issued to pay for the project.
The bonds will be repaid using Tax Increment Financing Proceeds.
|