406  Water Extension and 2nd Connection to Burlington Water


Phase II
Division II of the project has been awarded to S.G. Construciton for $745,248.00.  Construction of a water booster station including 2,000 sf masonry building, 2500 lineal feet of 12" water main, chemical addition, high service pumps and integrated utility control system.  To fund this project the City received a General Obligation Bond of $850,000.  These bonds will be paid mostly from Tax Increment Financing. 

Map of Water Construction Division II


Agency Rd - Washington Rd to HWY 406 Road

French-Reneker-Associates has been contracted to offer engineering services in connection with the portland cement concrete reconstruction of Agency Road from Washington Road to Highway 406.  Drawing and Specifications are to be placed on file April 2010.
Map of Proposed Recostruction of Agency Rd. from Washington Rd to HWY 406 Rd.

Drainage Improvements at Broadway Avenue and Agency Rd and Reconstruction of Intersection

French-Reneker-Associates has been contracted to offer engineering services in connection with the storm sewer from Division Street to the intersection of Agency Road and Broadway and the reconstruction of the Intersection.  Drawings and Specifications are to be placed on file June 15, 2010.

Wastewater Disinfection Facility Plan

Snyder & Associates has been contracted to offer engineering services in connection with the Wastewater Disinifection Facility Plan.  The City's wastewater treatment plant operates an AeroMod System in parallel with an aerated lagoon system whihc ultimately discharges into Spring Creek.  The Iowa Department of Natural Resources (IDNR) is currently increasing Water quality standards, and prior to the issuance of a revised NPDES permit, a USE Assessment and Use Attainability Analysis (UA/UAA) must be completed for the receiving stream.
At this time the UA/UAA for recreational uses has been completed for Spring Creek.  Analysis of the data has indicated a desigination of Secondary Contact Recreation Use to be appropriate for this receiving stream indicating that there likely will be more stringent bacterial permit limits in any future NPDES permit.
Also, an evaluation of the existing AeroMod blowers including possible modification, replacment, addition of a third blower for redundancy, and housing of the units within a building will be performed.
In order to determine what improvements may be necessary, as well as to obtain IDNR approval for improvements and to assist in qualificaiton for various financing assistance programs, a wastewater Facility Plan must be prepared.

 

Mall Road Reconstruction

The City has contracted with French-Reneker-Associates to explore the dedication of a portion of the Westland Mall Ring Road to the City of West Burlington.  French-Reneker is currently working with the property owners in connection with the extension of Huston and Van Weiss Streets on the north and east sides of Westland Mall.